Before Construction Started

Week 1 (06/23/03 - 06/27/03) : Excavation

Week 2 (06/30/03 - 07/04/03) : Concrete foundation poured

Week 3 (07/07/03 - 07/11/03) : Foundation cures, backfilled

Week 4 (07/14/03 - 07/18/03) : Framing

Week 5 (07/21/03 - 07/25/03) : Floor rebar, concrete floor poured, rafters, roofing started, doorway opening cut, window & patio door installation

Week 6 (07/28/03 - 08/01/03) : Roofing completed, electrical wiring, plumbing, clapboard, closet framed, insulation, soundproofing boards, blueboard

Week 7 (08/04/03 - 08/08/03) : Plastering, interior wood trim, electrical, heating/AC unit, French doors, closet doors

Week 8 (08/11/03 - 08/15/03) : Step below french doors, construction complete

House exterior after construction completed

Week 10 (08/25/03 - 08/29/03) : Interior and exterior painting

Week 11 (09/01/03 - 09/05/03) : Carpeting

Final Touches (10/03 - 11/03) : Draperies, wall rug hanging, pillow cover fabric, pool table